Causative Failure Factors of Delay in Heavy Equipment Procurement Management During the COVID-19 Pandemic: Malaysia Perspective

Causative Failure Factors of Delay in Heavy Equipment Procurement Management During the COVID-19 Pandemic: Malaysia Perspective

Kamal Muhammad Raini, Syuhaida Ismail, Mohamad Syazli Fathi, Halim Syah Hamzah
DOI: 10.4018/978-1-6684-5882-2.ch002
OnDemand:
(Individual Chapters)
Available
$37.50
No Current Special Offers
TOTAL SAVINGS: $37.50

Abstract

Since COVID-19 outbreak from Wuhan, China, rapid transformations worldwide demonstrate commitments in many countries towards new norms of social distancing and mask-compulsory trends of life. As the economic downturn affects public sector in terms of supply, services, and development projects, new challenges should be viewed as an opportunity for fundamental change, and public procurement reform as a catalyst for improving public policy and engaging civil society. Thus, this paper aims to examine the causative failure factors (CFF) of delay of mechanical asset procurement during pandemic from the Malaysian perspective. The literature reviews consider recent journal articles involving project management to understand the CFF of delay in overall project management and its relativity to mechanical asset procurement. Then, the paper suggests implementation of project management tools: Ishikawa diagram and PESTLE relatively to heavy equipment. Finally, this paper discusses the CFF to enable a comprehensive project scheduling to eliminate or avoid nuisance during project execution and completion.
Chapter Preview
Top

Literature Review

There are many studies related to construction industry such as case study of high-speed railway projects by(Nikjow et al., 2021), construction field case study by (Owusu & Aggrey, 2020), delay constructions projects risk and mitigation by (Abdul-Rahman et al., 2006; Assaf & Al-Hejji, 2006; Ramli et al., 2018; Yong & Mustaffa, 2012). However, when pandemic strikes Malaysia specifically, heavy equipment procurement is not being discussed thoroughly in separate perspective of views. Therefore, the main objective of paper is to examine the causative failure factors of delay in heavy equipment procurement management during COVID-19 in the case of Malaysia perspective. Hence, the literature reviews will focus on considering several recent journal articles involving project management to understand the causative failure of factors of delay in acquiring heavy equipment of public procurement. Then, these knowledge about the causative failure factors in public procurement during pandemic and how project management tools can help solve the issues.